Supersoil / Living Soil — Cycle calendar

Submitted by admin on

Cycle Calendar

What to do and when — Dogma Approach

This calendar is an operational map, not a rigid protocol. Living Soil operates on biological timelines that vary depending on genetics, pot size, environment, and grower experience.

Use it as a reference, not as an absolute rule.

Preparation phase — Before transplant

Substrate preparation is the most important phase of the entire cycle.

    • Day 1 — Mix Supersoil 4 Components with substrate (peat 60–80%, coco 20–40%). Add Root Connection. Moist substrate, not saturated, 18–24°C in darkness.
    • Weeks 1–2 — Sow Cover Crop. Maintain constant humidity. Aerate every 3–4 days.
    • Weekly — Water with Pure Molasses 1 ml/L once per week.
    • Week 3+ — Substrate ready: forest-like smell + visible white mycelium.

Vegetative phase

Phase of biological system stabilization. Minimal intervention.

    • Week 1 — Transplant + Root Connection. Only water.
    • Weeks 1–2 — Observation. Watering with lift-and-feel technique.
    • Weeks 2–3 — Pure Molasses 1 ml/L (once every other week).
    • Week 3 — Cover Crop management (optional trimming).
    • Week 4+ — Only water + alternating Molasses. LST and training.

Pre-flowering — 2 weeks before flip

    • Week -2 — Top Dress Flo applied on surface.
    • Week -1 — Molasses 1–1.5 ml/L + Ecobiobooster.
    • Week -1 — Root Connection (optional).
    • Photoperiod change — Start flowering / 12/12.

Flowering

Phase of maximum biological activity. The goal is to maintain balance.

    • Weeks 1–2 — Only water + alternating Molasses.
    • Weeks 2–3 — Second Top Dress Flo.
    • Week 3 — Ecobiobooster (with Molasses, tea, or irrigation).
    • Week 4 — Molasses + stop foliar Zeolite.
    • Weeks 5–6 — Second Ecobiobooster + optional Root Connection.
    • Weeks 6–7 — Only water + alternating Molasses.
    • Last 2 weeks — Reduced watering (optional), stop Molasses in final week.
    • Harvest — Cut and start substrate regeneration.

Important product notes

Pure Molasses

    • Standard 1 ml/L, once every other week
    • 1–1.5 ml/L when combined with Ecobiobooster
    • Do not use at every watering

Ecobiobooster

    • 2 applications: week 3 and weeks 5–6
    • Always combined with Molasses
    • Best applied as a biological tea

Pure Zeolite 10

    • Stop after week 4 of flowering
    • Avoid contamination of flowers

Top Dress Flo

    • Pots >8L: 2 applications
    • Pots <8L: possible 3rd application (week 5–6)

Quick product summary

    • Supersoil 4 Components — preparation + regeneration
    • Root Connection — transplant + pre-flowering + late flowering
    • Top Dress Flo — pre-flowering + mid-flowering
    • Pure Molasses — throughout the cycle (alternating rhythm)
    • Ecobiobooster — biological peaks (week 3 and 5–6)
    • Cover Crop — preparation + cycle management
    • Pure Zeolite — vegetative phase until early flowering